Renovation in phases on the same site as the 132/20 kV primary substation of Molini di Tures.
The HV section is made up of two cable line arrival uprights (with use of a multifunction hybrid group), a simple sorting bar, two transformer uprights and a system for compensated earthing of the neutral conductor on the MV side.
Construction of a single-storey building with an underground compartment for cable sorting
20 kV department composed of 20 air-insulated compartments and new command, control and protection system.