Installation of a transformation group consisting of a 220/20 kV transformer and a multifunction hybrid group, performed in gas-insulated mode without live parts in the air, due to the reduced insulation distances from the surrounding settlements.
Installation of the relevant protection and control system within the existing control room.
Connection of the complex to the Terna station by laying 220 kV underground cables.
Renovation of a civil building for garage use.