Variante all’elettrodotto esistente alla tensione di 20 kV CP Paluzza – cabina Valdajer
SECAB Società cooperativa – Paluzza (UD)

Variation to the existing power line at 20 kV voltage CP Paluzza - Valdajer cabin

Executive design, study of interferences and coordination for the execution of civil works and systems for the burial of the 20 kV line; construction supervision
Sum total of the work: € 898.000,00
Project: 2016
Work: 2019
Progress: work completed

Intervention aimed at burying an existing 20 kV overhead power line with LV branches and construction of 2 secondary MV/LV substations.

New underground route of approximately 3.3 km with sections on the road and on open ground, crossing watercourses, part in the town centre. 

Work in mountain municipality.